Home > News > UPCOMING ROAD CLOSURES

UPCOMING ROAD CLOSURES

12 July 2024

Share this article:share on twitter share on facebook

Update 10.10.2024 - Update on our bridge reconstruction works that are in progress on the A1088 (Bridge Farm Bridge). 

In the last few weeks, the concrete piling was installed, vegetation was removed, and the existing road was excavated to enable the existing bridge to be demolished, which happened a few weeks ago.

Unfortunately, in the last few days SCC have identified some issues with the concrete piles which have been installed. They are currently investigating and discussing these issues with the company who supplied the concrete, as well as other key stakeholders, to assess the impact of these issues and determine the best course of action to resolve them. 

Works have been temporarily paused for a brief period whilst this happens. This is consequently likely to have an impact on the duration of our programme of works, although the extent of this is yet to be confirmed. 

They are writing to provide as much advanced warning of these delays as possible.  However, at this early stage, they do not yet have a confirmed revised programme which captures a new anticipated completion date.  Their teams are working through alternative solutions, each of which have different construction and design requirements resulting in varying programme durations.

Due to the nature of works, it is unfortunately not safe to reopen the road whilst works are paused, and it is essential that they continue to work proactively to ensure that the scheme is completed as soon as possible.

The advanced warning signs advising of the road closure will remain in place, and the scheme dates on these will not be amended until we receive confirmation of the revised programme.

They sincerely apologise for the delay in the bridge replacement works and are conscious of the impact this will have on local communities. Please be reassured that we are continuing to work towards a solution minimise the overall duration of the works, so that the A1088 can be re-opened as soon as it is safe to do so.

Queries regarding works

Updates will be communicated via email and on their social media channels, as well as being provided on their dedicated Bridge Farm Bridge webpage which can be found here: https://www.suffolk.gov.uk/roads-and-transport/lorry-management/bridge-farm-bridge-a1088-stowlangtoft-bridge-replacement

Previous update

Work begins on the A1088 south of Ixworth on July 22nd

Works to replace the bridge along A1088 Bridge Farm Bridge, Stowlangtoft are programmed to commence on Monday 22 July 2024 and will continue until Friday 20 December 2024. During this time, the road will be closed to ensure the safety of highway users and our operatives.

For the duration of the closure, traffic will be diverted via A1088, A14, A143 and vice versa.

For more information about these and other road closures please see one.network

There may be times that essential emergency works are required to take place on the highway network without advanced notice – you can follow Suffolk Highways on Twitter for the latest emergency roadwork updates.

If you have any queries on the above, please contact us on 0345 606 6171.

Suffolk Highways

www.suffolk.gov.uk/highways